When you assign a resource to a PM schedule, that resource becomes responsible for completing each work order generated by the PM schedule. When TMS generates each work order, the resource is pre-assigned.
For example, you know that William Shakespeare is the technician (resource) who is always responsible for performing a preventive maintenance on the AHU-01 air handler unit. So, you assign William to the PM schedule for AHU-01.
Resources can be added to a new PM schedule or to an existing PM schedule. To add a resource to a PM schedule, follow these steps:
-
Open the PM schedule you want to add a participant to on the PM Edit page.
You can create a new PM schedule or use PM Edit or PM Query to locate an existing PM schedule.
-
Click the Procedures and Assignments tab.
-
In the Assignments area, do one of the following:
-
Click the New Resource button, select a resource from the drop-down menu, and then click Save. (You can also add a procedure from this dialog box, if needed).
-
Select a resource from the drop-down menu on the right side of the grid.
-
-
Click Save.