Issue Non-Inventory Materials for a Work Order
Non-Inventoried materials are those materials or parts that are typically not stored in a warehouse or other type of storage. You can create a non-inventoried material and issue it to a work order on the Work Order Edit screen.
You can reach the Work Order Edit screen by going to Work Orders > Edit and entering a valid Work Order Number, or by going to Work Orders > Query and searching for the work order.
To create a material issue for a non-inventoried material, follow these steps:
-
On the Work Order Edit screen, select the Materials tab, or other tab with the Material Issues grid, if you are using a custom form.
-
In the Material Issues area, click the New icon. The Material Issue screen opens.
-
In the Item Description field, enter a description of the non-inventoried material.
-
Tab or click off of the Item Description field.
-
TMS will ask if you are trying to create a new material or a material on-the-fly. Select Material on the Fly. Click Ok.
-
Enter a Quantity of the material being issued. The Quantity On Hand field does not update, since the material is non-inventoried.
-
To indicate who received the material, select a resource from the Received By drop-down menu.
-
In the Billable drop-down menu, indicate whether the material is billable (Yes or No).
-
Enter a cost for the material in the Average Cost field. Total Cost is updated automatically.
-
Select the Charge To tab.
-
If there is a procedure tied to the material issue, select the Procedure drop-down menu and select the procedure you want to associate with the material.
-
If there is one or multiple assets associated with the work order, the asset is shown in the Asset field. To tie the material issue to a different asset, select another one from the Asset drop-down menu.
On multiple asset work orders, the first asset on the work order is shown.
-
The Account field populates with the account tied to the work order. If you want to change the account, select a new account from the drop-down menu.
-
The Date Issued and Date Issued Time populate with the current date and time. Update either of these fields to indicate a different day and time for the material issue.
-
Enter any contract information that is necessary in the Contract, Contract Term, Term Value, and Contract Adjusted Cost fields.
Note:Any discount or markup applied to a material issue or time charge with a Contracts Term will not be applied to the Total Cost on the work order, or the Cost field on a material issue or time charge. The discount or markup will only be visible in the Contract Adjusted Cost field on the applicable material issue or time charge.
-
If the Show X12-850 fields on Material Issue option is enabled, see the Use the X12-850 Fields section for more information.
-
Enter any comments for the material on the Comments tab.
-
Click Save to submit the material issue, or Another to submit this material issue and enter another.