Create an Inventoried Material Issue
Inventoried materials are typically those materials or parts that you store in a warehouse or other type of storage. You can issue inventoried materials to a work order on the Work Order Edit screen.
You can reach the Work Order Edit screen by going to Work Orders > Edit and entering a valid Work Order Number, or by going to Work Orders > Query and searching for the work order.
To create a material issue for an inventoried material, follow these steps:
-
On the Work Order Edit screen, select the Materials tab, or other tab with the Material Issues grid, if you are using a custom form.
-
In the Material Issues area, click New. The Material Issue screen opens.
-
Select a Warehouse.
-
Enter an Issue Item number or use the Lookup button to search for and select the material you need to issue to the work order.
-
In the Billable drop-down menu, indicate whether the material is billable (Yes or No).
-
Enter a Quantity of the material being issued. The Quantity On Hand field is updated automatically.
-
To indicate who received the material, select a resource from the Received By drop-down menu.
-
The Average Cost value and the Total Cost populate automatically. If you need to enter a different cost for the material, do so in the Average Cost field.
-
Select the Charge To tab.
-
If there is a procedure tied to the material issue, select the Procedure drop-down menu and select the procedure you want to associate with the material.
-
If there is one or multiple assets associated with the work order, the asset is shown in the Asset field. To tie the material issue to a different asset, select another one from the Asset drop-down menu.
On multiple asset work orders, the first asset on the work order is shown.
-
The Account field populates with the account tied to the work order. If you want to change the account, select a new account from the drop-down menu.
-
The Date Issued and Date Issued Time populate with the current date and time. Update either of these fields to indicate a different day and time for the material issue.
-
Enter any contract information that is necessary in the Contract, Contract Term, Term Value, and Contract Adjusted Cost fields.
Note:Any discount or markup applied to a material issue or time charge with a Contracts Term will not be applied to the Total Cost on the work order, or the Cost field on a material issue or time charge. The discount or markup will only be visible in the Contract Adjusted Cost field on the applicable material issue or time charge.
-
If the Show X12-850 fields on Material Issue option is enabled, see the Use the X12-850 Fields section for more information.
-
Enter any comments for the material on the Comments tab.
-
Click Save to submit the material issue, or Another to submit this material issue and enter another.