PPM Suppressions
Suppress work order generation for a PPM schedule when you want to prioritize a different schedule for associated assets. Designate a time period in which to keep the suppression active. For example, you can prioritize a lower-frequency schedule like annual maintenance over a higher-frequency schedule like monthly maintenance and designate a time period in which the monthly schedule won't generate work orders.
Suppress PPM
-
Go to Admin > PPM Manager and open the PPM schedule you want to prioritize over another one.
-
Open PPM Suppressions and select Add PPM builder to suppress.
-
Select one or more PPMs to suppress.
-
Click Select builders.
-
In Suppression method, select Same day or Same month to define when suppression applies.
-
Enter the Number of days prior and the Number of days after scheduled work order generation that suppression should be active.
-