Task Dates
Siterra allows you to set and track multiple task dates, each with a specific significance. The table below lists these task dates and their definitions.
Date | Definition |
---|---|
Actual Date |
When a subtask is completed. |
Baseline Date |
When a task was originally expected to be completed. |
Completion Date |
When a task is completed. |
Forecast Date |
When a task is expected to be completed. |
Manual Date |
When a task is manually marked as completed rather than by the completion of all of its subtasks. |
System Date |
A placeholder for use in special cases such as if a task is completed but a predecessor task is not completed yet, so the current task cannot yet be marked officially completed. |