Fullscreen Image

Mark Multiple Approved

Users with certain permissions can simultaneously mark multiple subtasks as Approved in the Schedule section.

  1. Navigate to a Project home page.

  2. Scroll to the Schedule section.

  3. In the toolbar of the Schedule section, click Multiple, then click Mark Multiple Approved.

    A new window appears.

  4. Select the check box next to each desired subtask.

  5. Click OK.

    The Project home page refreshes, and the selected subtasks are marked as Approved.

Percentage & Complete

In the Project, you can see a section that displays what percentage of completion the Task is at in a field labeled Percentage Complete. This percentage is calculated based on which percentage of the total Duration fields located in the Project Schedule have been approved as complete.