Lock a Schedule

You can manually lock a date on schedule. Locking a date prevents the task from being affected if changes are made to a predecessor task.

Lock a task date:

  1. Navigate to a Project home page.

  2. Navigate to the Edit Schedule section.

  3. Scroll to the desired task.

  4. Select the check box in the Lock column for the task.

  5. Click Commit Changes.

    Changes made to the Project Schedule are committed.

Lock the entire Project Schedule:

  1. Navigate to a Project home page.

  2. Navigate to the Edit Schedule section.

  3. In the toolbar of the Edit Schedule section, click Lock.

    All check boxes in the Lock column are automatically selected.

  4. Click Commit Changes.

    Changes made to the Project Schedule are committed.