Lock a Schedule
You can manually lock a date on schedule. Locking a date prevents the task from being affected if changes are made to a predecessor task.
Lock a task date:
-
Navigate to a Project home page.
-
Navigate to the Edit Schedule section.
-
Scroll to the desired task.
-
Select the check box in the Lock column for the task.
-
Click Commit Changes.
Changes made to the Project Schedule are committed.
Lock the entire Project Schedule:
-
Navigate to a Project home page.
-
Navigate to the Edit Schedule section.
-
In the toolbar of the Edit Schedule section, click Lock.
All check boxes in the Lock column are automatically selected.
-
Click Commit Changes.
Changes made to the Project Schedule are committed.