Set a Manual Completion Date
If a task is completed prior to the Forecast Date, users with certain permissions can set a manual Completion Date on the task.
-
Navigate to a Project home page.
-
In the Schedule section, scroll to the desired task.
-
Click the Task icon next to the desired task, then click Set Manual Completion Date.
The section expands to display a form.
-
Enter a date in the Manual Date field.
-
Click Submit.
The task is completed, and the date entered appears in the Completion column for the task.