Add Ad Hoc Dependencies
-
Navigate to a Project home page.
-
Scroll to the Schedule section.
-
In the Schedule section, click the Task icon next to the desired task, then click Manage Dependencies.
A new window appears.
-
Click Add Task Dependency.
The section expands to display a form.
-
Complete the form. The fields in the form must be completed in the following order:
-
Select Parent Type
-
Select Object (e.g., if Site is chosen in the Select Parent Type field, the Select Object field automatically appears as Select Site)
-
Select Project
-
Select Task
-
-
When the form is complete, click Save.
The ad hoc task dependency is created.