Fullscreen Image

Add Ad Hoc Dependencies

  1. Navigate to a Project home page.

  2. Scroll to the Schedule section.

  3. In the Schedule section, click the Task icon next to the desired task, then click Manage Dependencies.

    A new window appears.

  4. Click Add Task Dependency.

    The section expands to display a form.

  5. Complete the form. The fields in the form must be completed in the following order:

    • Select Parent Type

    • Select Object (e.g., if Site is chosen in the Select Parent Type field, the Select Object field automatically appears as Select Site)

    • Select Project

    • Select Task

  6. When the form is complete, click Save.

    The ad hoc task dependency is created.