Add Task
-
Tap a project tile.
-
In Tasks, tap Add.
-
Complete the required fields.
-
Parent Group
-
Task Name
-
Status
-
Percent Complete
-
Actual Start Date: The date the task started
-
Actual Duration: The number of days this task took. This refers to working days only. A duration of 1 means the task was finished the same day it started.
-
Original Start Date: The baseline start date
-
Projected Start Date: The start date you are aiming for
-
-
Enter Comments if required.
-
Tap Save.
-
To upload the change, tap Update Project.